Cambodia: 230kV Kampong Cham – Kratie Transmission System Project<br/><span class="design1">(Lenders Engineer)</span>
End User Electricite Du Cambodge (EDC), Cambodia Project Title 230kV Kampong Cham – Kratie Transmission System Project Year 2017/18 Project Scope Construction two new 230/115/22kV substations namely Kratie and Kampong Cham connected by an approximately 98km double circuit 230kV transmission line linking these substations. Our Scope Provide services as Independent Engineer (IE) to review and […]
Malaysia: 132/33kV Sungai Mati Transformer Replacement Scheme<br/><span class="design1">(Design Review and Technical Assurance)</span>
End User Tenaga Nasional Berhad (TNB) Malaysia Project Title 132/33kV Sungai Mati Transformer Replacement Scheme Year 2015 Project Scope Supply, erect and commissioning of 2 new 132kV Transformer bays, 132/33kV 90MVA Transformers, ancillary equipment and associated civil works for the replacement of 45MVA existing transformers Our Scope Site survey, preparation of technical specifications, cost estimates, […]
Singapore: Transformer Independent Review<br/><span class="design1">(Specialist Review)</span>
End User Bureau Veritas Project Title Transformer Independent Review Year 2015 Project Scope The end client Singapore Power Grid Ltd had a dispute with their main contractor on supply of 230/66/22kV 200MVA Power Transformer Our Scope Provide an independent review on 230/66/22kV 200MVA Power Transformer technical specifications and factory acceptance test reports. Identify any ambiguous […]
Kenya: Consultancy Services For The Project Management And Supervision Of The Lamu-Kitui-Nairobi East 520km Double Circuit 400kV Transmission Lines And Substations<br/><span class="design1">(Owners Engineer)</span>
End User Kenya Electricity Transmission Company (KETRACO) Project Title Consultancy Services for the Project Management and Supervision of the Lamu-Kitui-Nairobi East (520 km) and Dongo Kundu – Mariakani (50 km) Double Circuit 400 kV Transmission Lines and Substations Year 2014 Project Scope The Government of Kenya plans to add more than 5000 MW of generation […]
Malaysia: 275kV Jeli Extension<br/><span class="design1">(Design Review and Technical Assurance)</span>
End User Tenaga Nasional Berhad (TNB) Malaysia Project Title 275/132/33kV Jeli AIS Substation Extension Year 2018/19 Project Scope The project involves construction of: 2 x 275kV bays 1 x 132/33kV 45MVA Transformer Protection, Control and RTU System Building and associated Civil Works Our Scope Review and reorganization of contract documents Review of contractor’s design Attending […]
132/33kV Grid Transformers Replacement<br/><span class="design1">(Project Development, FEED & Detailed Design)</span>
End User Scottish and Southern Electricity Networks Project Title Replacement of 132/33kV Grid Transformers A1MT, A2MTA, A2MTB at 132/33kV Havant Substation Year 2019/20 Project Scope Replacement of existing 132/33kV 90MVA and 45MVA transformers in stages. The design scope covers Stage 1 concept design to develop a high-level P&C concept as defined in the Technical Report […]
33kV Network Reinforcement<br/><span class="design1">(Project Development, FEED & Detailed Design)</span>
End User Scottish and Southern Electricity Networks Project Title 33kV network reinforcement between Ascot , Bracknell and MVEE substations Year 2019/20 Project Scope Installation of new 6 panel 33kV indoor switchboard at Ascot substation and to establish 2 new 33kV cable circuits to MVEE substation and remote end protection modifications at Bracknell, Sunninghill and Chobham […]
400kV Switchgear Refurbishment<br/><span class="design1">(Design Review and Technical Assurance)</span>
End User National Grid plc Project Title Lot 3 – Switchgear Replacement Year 2017 Project Scope Replacement of old Conventional Air Blast (CAB) Circuit Breakers from 132kV up to 400kV that were installed back in 1960’s that has reached their useful asset life or have failed the condition assessment. The project site involves 10 substations […]
Review of Existing 33kV Protection Settings<br/><span class="design1">(Specialist Studies)</span>
End User Scottish and Southern Electricity Networks Project Title Protection Task Force – Review of existing 33kV protection settings for the South network Year 2019 Project Scope Review of existing 33kV protection settings and grading studies involving SSEN South of England distribution network for Burghfield and Thatcham regions. Our Scope Undertake manual settings calculations in […]
Rechargeable Customer Connections<br/><span class="design1">(Project Development, FEED & Detailed Design)</span>
End User Scottish and Southern Electricity Networks Project Title Rechargeable Customer Connections (from 11kV to 132kV) Year 2016/18 Project Scope Renewable energy projects involving PV Solar, Battery Storage, AC Generators and Customer connections involving Data Centers in the South East of England. Our Scope Provide technical support for new connection enquiries from application right to […]