Project Scope
Replacement of indoor 11kV and outdoor 33kV switchgears for various sites as part of SSEN major project investments.
Our Scope
The protection scope involves design for new 11kV and 33kV protection system and wiring modifications on the existing Transformer protection panels to interface with the new HV and LV protection relays, interfacing with the existing AVC scheme, new 110V DC battery and charger for control and tripping, new 24V DC battery and charger for RTU, new dry type NER resistor, new RTU telecontrol system.
To deliver detail design drawings and project scoping documents for SSE major projects delivery team, and to support the project delivery phase to final completion and commissioning.
Our Key Attributes
- Proposed a temporary 11kV board solution to overcome outage constraints and staging of the works.