End User
Tenaga Nasional Berhad (TNB) Malaysia
Project Title
275/132/33kV Jeli AIS Substation Extension
Year
2018/19
Project Scope
The project involves construction of:
- 2 x 275kV bays
- 1 x 132/33kV 45MVA Transformer
- Protection, Control and RTU System
- Building and associated Civil Works
Our Scope
- Review and reorganization of contract documents
- Review of contractor’s design
- Attending Type Tests, Factory Acceptance Tests and Site Tests for Substation, Transmission Line and Underground Cable
- Project management and supervision of construction of the Substation, Transmission Lines and Underground Cable
- Final Inspection, Testing and Commissioning
- Final Project Completion Reports