Client
UK Power Networks
Project Title
Protection schemes design for 132/33kV grid substation (Detailed Design)
Year
2020 to 2026
Project Scope
Provided detailed design for protection secondary scheme for connection projects involving 132kV grid substations.
- Warley 132kV Grid substation
- Shenfield 132kV Grid substation
- Rivenhall 132kV Grid substation
- Braintree 132kV Grid substation
Our Scope
Conduct site visit, review existing drawings and prepare full set of detailed design schematics:
- Main Connection & Protection (GREEN & RED)
- AC & DC Schematic (GREEN & RED)
- Wiring Diagrams (GREEN & RED)
- Multicore Cable Block Diagram (GREEN & RED)
- Termination Schedule (GREEN & RED)
- SCADA Multicore Cable Block Diagram (GREEN & RED)
- SCADA Schedule (GREEN & RED)
- Interface Marshalling Box